Feedback: Industry update on CoCT IPP procurement court case

View this email in your browser

 

Webinar feedback (20 May 2020) 
Industry update on the
City of Cape Town court case to procure energy from Independent Power Producers

 

 

Dear energy stakeholder, 

You are receiving this email because you joined us for the webinar on 20 May 2020, or indicated that you would like to receive the recording of the session post-event. 

Topic: In the light of the recent developments surrounding the City of Cape Town's court case to be allowed to procure its own power from Independent Power Producers, we hosted a virtual event with Kadri Nassiep, City of Cape Town Executive Director, Energy and Climate Change Directorate. 
 

 

 

 

As mentioned, South African Minister of Mineral Resources and Energy, Gwede Mantashe, has gazetted for public input the draft amendments to the Electricity Regulations on New Generation Capacity. The draft amendments are aimed at clarifying the regulatory regime applicable to municipalities for procurement or development of power generation capacity. The public has 30 days from the date of gazette to provide comments.

Public comments should be addressed to:


Director-General, Department of Mineral Resources and Energy,
Private Bag X96,
Pretoria 0001,
Matimba House 192 Visagie Street, Pretoria

Or by email NewGenRegs2020@energy.gov.za  

The draft regulations can be accessed and downloaded on government gazette, or www.energy.gov.za  & www.dmr.gov.za  

 

Image removed by sender. Website

Image removed by sender. LinkedIn

Image removed by sender. Twitter

Our mailing address is:
energy@green-cape.co.za

Want to change how you receive these emails?
You can update your preferences or unsubscribe from this list.

Image removed by sender.

Add Comment

Click here to post a comment

Leave a Reply

WP Twitter Auto Publish Powered By : XYZScripts.com