Coal Eskom

Medupi start-up delayed to mid-2014

By: Terence Creamer | 8th July 2013 | Engineering News

State-owned power utility Eskom confirmed on Monday that it would not be in a position to meet the end of year deadline for the flow of first power from the Medupi power station.

CEO Brian Dames reported that, following an independent assessment and fresh delays to the control and instrumentation contract, a new, “realistic”, timeframe had been set for the second half of 2014.

The power station was meant to supply first power to the grid by December 2013, a deadline reaffirmed as non-negotiable earlier this year by Public Enterprises Minister Malusi Gigaba.

Dames also confirmed that the cost of the project had increased from R91.2-billion to R105-billion, excluding interest during construction. In 2008, when the main boiler, turbine and civil contracts had been placed, Medupi’s cost was estimated at R87-billion and was revised to R91.2-billion in June 2012.

SOURCE: http://www.engineeringnews.co.za/article/medupi-start-up-delayed-to-mid-2014-costs-rise-to-r105bn-2013-07-08