Energy Regulator approves 40 MW solar licence for Gold Fields' South Deep

Photo by Creamer Media

25TH FEBRUARY 2021

BY: CREAMER MEDIA REPORTER

ARTICLE ENQUIRY      SAVE THIS ARTICLE      EMAIL THIS ARTICLE

FONT SIZE: +

The National Energy Regulator of South Africa (Nersa) announced on Thursday that the Energy Regulator, at its meeting held on February 25, approved the issuance of a generation licence for a 40 MW solar photovoltaic (PV) plant to be developed at the South Deep gold mine, in Gauteng.

The licence was granted to GFI Joint Venture Holdings Proprietary Limited and Gold Fields Operations Limited (South Deep Joint Venture) to operate a generation facility to be constructed in Westonaria, south-west of Johannesburg.

ADVERTISEMENT

The application, which was the subject of a virtual public hearing on December 3, was received on June 18, 2020, and Nersa said it could not be processed within the required timelines due to the Covid-19 pandemic.

"There have been unverified and misleading media reports that Nersa has delayed processing this application since 2017.

ADVERTISEMENT

"It must be indicated that South Deep submitted its first application for a generation licence of a 40 MW solar plant in 2017.

"However, this application could not be processed because it was not compliant with the requirements of the Electricity Regulation Act, 2006," Nersa said in a statement.

It added that the application also did not have Ministerial approval to deviate from the Integrated Resource Plan (IRP), as was required by Section 10(2)(g) of the Electricity Regulation Act, 2006.

In addition, the South Deep gold mine did not have environmental authorisation as required by the National Environmental Management Act, 1998.

"Nersa engaged with and guided South Deep gold mine on how to ensure that the application is compliant with the legal requirements to enable Nersa to process the application."

On February 1, 2020, Mineral Resources and Energy Minister Gwede Mantashe issued approval for deviation from the IRP for self-generation projects of any capacity.

"Following this approval, South Deep Joint Venture submitted a compliant application on June 18, 2020."

The application was then processed through Nersa's regulatory processes.

The 40 MW solar PV plant will be constructed on the same site as the South Deep mine and all power generated by the plant will be consumed by the mine. 

STAY IN THE LOOP

Subscribe to our free newsletter.

Business Report 1 July 2012. Optimal Energy chief executive Kobus Meiring is a disappointed man. The company is the developer of South Africa’s electric car but it officially closed on Friday with the loss of about 60 jobs. This follows its failure to get further funding from the government and the Industrial Development Corporation (IDC)... http://www.iol.co.za/business/business-news/why-sa-s-electric-car-is-not-going-anywhere-1.1331580#.T_E37xcjGq8

Related Posts

  • By Dan MurtaughIn some ways solar is having too much success in China.Installing panels has become so popular that Chinese officials drafted By Dan Murtaugh Solar outshines wind to lead China’s clean-energy transition In some ways solar is having too much success in China. Installing panels has become so popular that Chinese officials drafted regulations […]

  • By Todd WoodyElectrify Your LifeWith the first-ever US climate bill approaching passage in Congress, it’s time to reconsider the calculus fo By Todd Woody Electrify Your Life With the first-ever US climate bill approaching passage in Congress, it’s time to reconsider the calculus for when American households think about going solar. If the bill is passed into law, that transition will instantly […]

  • By Ethan van Diemen 26 Jul 2022 original article here President Cyril Ramaphosa on Monday night announced what he called an ‘energy action plan’ to tackle South Africa’s power crisis. This is what the plan entails. On Monday night, President Cyril Ramaphosa announced a set of actions to respond to South Africa’s yearslong energy crisis. “The […]

  • Ramaphosa doubles next renewables round, scraps 100 MW cap on distributed plant and moots feed-in tariff as he unveils load-shedding crisis response President Cyril Ramaphosa 25TH JULY 2022 BY: TERENCE CREAMER CREAMER MEDIA EDITOR ARTICLE ENQUIRY      SAVE THIS ARTICLE      EMAIL THIS ARTICLE FONT SIZE: –+ President Cyril Ramaphosa unveiled several far-reaching interventions – including a doubling in the allocation for the next renewables […]