Eskom CEO André de Ruyter has appealed for an immediate easing of regulatory impediments to the introduction of both immediately available capacity of about 500 MW and the accelerated procurement, or introduction, of the generation capacity required to ease the now constant risk of load-shedding.
De Ruyter made this “call to arms” after the utility declared Stage 4 load-shedding at short notice on Tuesday morning and indicated that the rotational cuts would continue until 5:00 on Friday morning, owing to high levels of unplanned breakdowns of more than 15 600 MW.
“There are a number of steps that can be taken on an urgent basis by a number of parties [and] clearly Stage 4 load-shedding is a call to arms to address these issues,” he said during a briefing.
One of these actions included receiving authorisation for a so-called ‘standard offer’, through which Eskom would seek bids from small private generators to sell their surplus electricity into the grid under three-year contracts.
“The idea is for us to enter into these standard-offer agreements and fund these through the normal cost-recovery arrangements,” De Ruyter said, reporting that the Eskom board had approved the instrument in August.
For the standard offer to be activated, however, Eskom required a Section 34 determination under the Electricity Regulation Act to enable it to buy the electricity, as well as an exemption from some of the requirements of the Preferential Procurement Policy Framework Act.
In addition, the utility would require the concurrence of the National Energy Regulator of South Africa (Nersa), as well as the regulator’s assurance that it could recover the costs through the tariff.
“We are waiting for a variety of approvals from the National Treasury, Nersa, as well as from the Department of Mineral Resources and Energy (DMRE) to bring this online.
“This could yield about 500 MW to 600 MW – so not huge in the bigger scheme of things, but if you add up all of the other initiatives that we are proposing, we are looking at [reducing] one or two stages of load-shedding.”
The other initiatives referred to included making amendments, through the Independent Power Producer (IPP) Office, to the contracts in place with existing IPPs to unlock a further 200 MW that these generators are currently contractually disallowed from injecting into the grid.
In addition, there is potential, also through the IPP Office, to facilitate IPP plant improvements that could add a further 200 MW in the near term.
In parallel, Eskom was working to debottleneck the evacuation infrastructure servicing those IPPs to potentially unlock a further 200 MW to 300 MW.
Asked by Engineering News whether these proposals had been made formally to both the Department of Public Enterprises (DPE) and the DMRE, De Ruyter stressed that all its communications with government was being channeled through the DPE, including those that required action from either the National Treasury or the DMRE.
“So, I think that the steps that are required to resolve the crisis are known, they have been communicated and we have emphasised the need for urgency.”
In the longer-term, however, new generation capacity was required to close a prevailing supply gap of between 4 000 MW and 6 000 MW.
“We need more capacity to be added to the grid as soon as possible, and we should remove all roadblocks that stand in the way of adding that capacity as quickly as possible.”
In the process, South Africa could “pivot from our historical coal-fired base, which is not as reliable and as available as it should be, to low- and no-carbon forms of electricity generation”.
Such a transition, De Ruyter added, could be partly funded through concessional finance being made available in the wake of the COP26 climate talks in Glasgow, Scotland.
South Africa has received an $8.5-billion transition offer, which is currently the subject of government-to-government negotiations with the European Union, Germany, France, the UK, and the US.
STAY IN THE LOOP
Subscribe to our free newsletter.
Tangled web of Eskom has little to do with electricity By MJ (Thinus) Booysen Follow 14 Dec 2022 2 Professor MJ (Thinus) Booysen is Research Chair in Internet of Things and Director of the MTN Mobile Intelligence Research Laboratory in the Faculty of Engineering, Stellenbosch University: www.thinus.co.za The technical and economic challenges in South Africa’s energy crisis […]
By Ethan van Diemen 26 Jul 2022 original article here President Cyril Ramaphosa on Monday night announced what he called an ‘energy action plan’ to tackle South Africa’s power crisis. This is what the plan entails. On Monday night, President Cyril Ramaphosa announced a set of actions to respond to South Africa’s yearslong energy crisis. “The […]
4TH JULY 2022 BY: TERENCE CREAMER original article here Electricity utility Eskom is developing a Web-based portal that will offer real-time visibility of locations in South Africa where new generators can be immediately or easily connected to the grid. The utility has, for the past three years, been arguing that between 4 000 MW and 6 000 MW of additional capacity is […]
By Queenin Masuabi 04 Jul 2022 original article here The ANC’s National Executive Committee (NEC) sat for a virtual meeting on Monday in which a number of key issues were discussed – including Eskom and its inability to keep the lights on. Conversations around load shedding and Eskom took place on Monday during the ANC’s […]